CHEM 107/Fall 2008
Instructor: Mr. Suiter
E-mail: suiterr@winthrop.edu
Office: 109A
Office Hours:
Date: Week of |
Schedule |
Assignments due |
9/1 |
Introduction Cooperative Lab I: (Project 1: Density) Lab Bench Check-in |
Cooperative lab I experimental plan due at end of lab |
9/8 |
Safety Quiz Cooperative Lab I: (Project 1: Density) |
|
9/15 |
Quiz: Project I Cooperative Lab II: (Project 11: Identification, Properties, and Synthesis of an Unknown Ionic Compound)
|
Cooperative Lab I report due at
beginning of lab Cooperative Lab II experimental plan due at end of lab |
9/22 | Cooperative Lab II - Experimental work | Weekly report 1 |
9/29 | Cooperative Lab II - Experimental work | Weekly report 2 |
10/6 |
Quiz: Project II Cooperative Lab III: (Project 5: Designing a Calcium Supplement) |
Cooperative lab II report due
beginning of lab
Cooperative lab III experimental plan due at end of lab |
10/13 | Cooperative Lab III- Experimental work | Cooperative lab III |
10/20 | Fall Break | No Lab |
10/27 |
Quiz: Project III Cooperative Lab IV: (Project 12: Hot and Cold) |
Cooperative lab III report due at beginning of lab Cooperative lab IV experimental plan due at end of lab |
11/3 | Cooperative IV- Experimental work | Weekly report 1 |
11/10 | Cooperative IV- Experimental work | Weekly report 2 |
11/17 |
Quiz: Project IV Course Evaluation Lab-Bench check-out |
Cooperative lab IV report due at
beginning of lab
|
11/24 | Thanksgiving | No Lab |
12/1 | Molecular Modeling Lab I | Molecular modeling report due |
This is a tentative schedule. It is subject to change.